CompTIA Network+ N10-008 – Question366

A Chief Executive Officer and a network administrator came to an agreement with a vendor to purchase new equipment for the data center. A document was drafted so all parties would be informed about the scope of the project before it started. Which of the following terms BEST describes the document used?

A. Contract
B. Project charter
C. Memorandum of understanding
D. Non-disclosure agreement

Correct Answer: B