The management team has instituted a 48-hour RTO as part of the disaster recovery plan. Which of the
following procedures would meet the policy's requirements?
A. Recover all systems to a loss of 48 hours of data.
B. Limit network downtime to a maximum of 48 hours per year.
C. Recover all systems within 48 hours.
D. Require 48 hours of system backup maintenance.
following procedures would meet the policy's requirements?
A. Recover all systems to a loss of 48 hours of data.
B. Limit network downtime to a maximum of 48 hours per year.
C. Recover all systems within 48 hours.
D. Require 48 hours of system backup maintenance.