CompTIA Project+ PK0-004 – Question096

A company has dictated project scope changes but has stated that the original budget still applies. Which of the following will MOST likely be impacted by the changes?

A.
Quality
B. Regulations
C. Schedule
D. project team

Correct Answer: C

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133