CompTIA Project+ PK0-004 – Question097

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project's success?

A.
Reduce the scope
B. Increase the budget
C. Decrease staff
D. Update the WBS