CompTIA Project+ PK0-004 – Question098

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

A.
Transfer
B. Accept
C. Avoid
D. Mitigate

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238