The PM is preparing for the planning phase kickoff meeting. It is imperative for the team to focus during the meeting on the expected outcomes.
Which of the following best describes what the PM should work on FIRST?
A. Project charter
B. Project schedule
C. Meeting agenda
D. Responsibility assignment matrix
E. Risk register
Which of the following best describes what the PM should work on FIRST?
A. Project charter
B. Project schedule
C. Meeting agenda
D. Responsibility assignment matrix
E. Risk register