CompTIA Project+ PK0-004 – Question151 A project is taking more effort than anticipated. Which of the following constraints will MOST likely be affected?A. ScopeB. TimeC. QualityD. Cost Show Answer Hide Answer Correct Answer: D Explanation: Reference: https://programsuccess.wordpress.com/2011/05/02/scope-time-and-cost… Post navigation CompTIA Project+ PK0-004 – Question150CompTIA Project+ PK0-004 – Question152