CompTIA Project+ PK0-004 – Question163

A project has a of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?

A.
Add the required work to complete the project behind $892,500.
B. Evaluate the impact and justify adding new work to the project.
C. Obtain approval from the CCB.
D. Request a budget increase of $170,000.

Correct Answer: C