CompTIA Project+ PK0-004 – Question171

Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?

A.
Risk avoidance:e
B. Risk transfer
C. Risk exploitation
D. Risk mitigation

Correct Answer: B