CompTIA Project+ PK0-004 – Question183

The project manager is reviewing the earned value of work completed compared to the planned value and is representing it in a dollar figure.
This type of analysis is an example of which of the following?

A.
Cost performance index
B. Risk mitigation
C. Schedule variance
D. Cost variance

Correct Answer: C