CompTIA Project+ PK0-004 – Question189 Resources for a project report to a project manager and a functional manager. The organizational structure is:A. MatrixB. Ad hocC. FunctionalD. Projectized Show Answer Hide Answer Correct Answer: A Post navigation CompTIA Project+ PK0-004 – Question188CompTIA Project+ PK0-004 – Question190