CompTIA Project+ PK0-004 – Question194

Which of the following tools would a project manager use to determine the root cause of an issue?

A.
Pareto Chart
B. Ishikawa Diagram
C. Histogram
D. Monte Carlo Analysis

Correct Answer: B