A subcontractor has submitted design documentation on the deliverable due date, but it will require rework. The activity is on the critical path of the project schedule. Which of the following should the project manager do NEXT?
A. Determine the expected duration of the rework and complete a charge request to modify the project baselines.
B. Notify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
C. Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
D. Update the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.
A. Determine the expected duration of the rework and complete a charge request to modify the project baselines.
B. Notify the project sponsor to schedule and facilitate a team meeting to rework the design documentation.
C. Determine the expected duration of the rework with any associated quality control activities and add the duration to an updated version of the WBS.
D. Update the master project schedule, and distribute it all stakeholders in accordance with the project communications plan.