CompTIA Project+ PK0-004 – Question231

A key stakeholder asks the project manager for additional features. Which of the following documents should the project manager refer to before responding to this request?

A.
Process diagram
B. Change control plan
C. Balanced scorecard
D. SWOT matrix

Correct Answer: B