CompTIA Project+ PK0-004 – Question017

Which of the following activities are associated with the closing phase of a project? (Choose two.)

A.
Risk mitigation
B. Archiving of project documents
C. Tracking of expenditures
D. Lessons learned
E. Quality assurance

Correct Answer: BD

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 338, 339