CompTIA Project+ PK0-004 – Question265

Which of the following are the BEST risk analysis tools to determine a project's risk level? (Choose two.)

A.
Fishbone diagram
B. RACI matrix
C. Monte Carlo
D. Process flowchart
E. Expert judgment
F. Project dashboard

Correct Answer: CE