CompTIA Project+ PK0-004 – Question288

A project team is in the process of risk planning. One of the team members identifies a weather-related risk, which may cause delivery delays.
Which of the following is the BEST risk response strategy?

A.
Exploit
B. Enhance
C. Mitigate
D. Communicate

Correct Answer: C