CompTIA Project+ PK0-004 – Question295

Which of the following communication methods and target audiences would a project manager MOST likely select for briefings as required during a business continuity incident?

A.
Email and instant messaging to project team members and the project team members and the project sponsor
B. Text messages to and voice conferences with all stakeholders and project team members
C. Video conferences with key stakeholders and the project champion
D. Instant messaging to the project coordinator and project scheduler

Correct Answer: C