A fire occurred in the production facility over the weekend, affecting the machinery being used to produce a deliverable. No injuries were reported.
Which of the following is MOST appropriate for the project manager to do NEXT?
A. Refer to the contingency plan
B. Conduct an immediate emergency team meeting
C. Perform a SWOT analysis
D. Implement the risk response plan