CompTIA Project+ PK0-004 – Question318

A project manager is analyzing the cost variances produced when comparing two different projects completions.

Which of the following factors could be causing the increased variance for the four-month projects? (Choose two.)

A.
Increased resource productivity
B. Increased resource allocation
C. Increased schedule variance
D. Increased labor cost
E. Increased labor overhead

Correct Answer: DE