A project manager is meeting with top management executives and presenting a project status report. The Chief Information Officer (CIO) and other executives complain that the meeting is taking too long and not providing summary information on the project's progress.
Which of the following should the project manager be presenting?
A. Project issue
B. Project dashboard
C. Project schedule
D. Project milestone
Which of the following should the project manager be presenting?
A. Project issue
B. Project dashboard
C. Project schedule
D. Project milestone