CompTIA Project+ PK0-004 – Question326

A PM has notified the project team of an immediate project relocation. Of which of the following triggers is this MOST likely a result? (Choose two.)

A.
Business continuity response
B. Resource changes
C. Disaster recovery response
D. Risk response
E. Gate review

Correct Answer: AB