CompTIA Project+ PK0-004 – Question357 Which of the following is the MOST important component against which the project manager can analyze project performance?A. Burn rateB. Project baselinesC. KPIsD. Budget Show Answer Hide Answer Correct Answer: C Post navigation CompTIA Project+ PK0-004 – Question356CompTIA Project+ PK0-004 – Question358