CompTIA Project+ PK0-004 – Question382

A project manager determines deliverables are not meeting customer specifications. During which of the following project phases is this determination MOST likely to happen?

A.
Monitor and control
B. Execution
C. Closing
D. Planning

Correct Answer: A