A project needs two more months of work to be completed, but the deadline is in 35 days. The project manager heard the company recently hired an experienced person. The project manager scheduled a meeting with the functional manager to negotiate bringing the experienced person to the team. Which of the following strategies is the project manager trying to apply?
A. Exploit
B. Mitigate
C. Accept
D. Transfer
A. Exploit
B. Mitigate
C. Accept
D. Transfer