Risk ID 2 has occurred.
Which of the following ways should the project manager update the risk register?
A. Add a column for probability and set risk 2 at 100%
B. Change the risk 2 response to backups restored
C. Change the risk 2 status to issue
D. Change the risk 2 owner to PM
Which of the following ways should the project manager update the risk register?
A. Add a column for probability and set risk 2 at 100%
B. Change the risk 2 response to backups restored
C. Change the risk 2 status to issue
D. Change the risk 2 owner to PM