CompTIA Project+ PK0-004 – Question423

The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?

A.
Gantt chart
B. Scatter chart
C. Run chart
D. Process diagram

Correct Answer: A