A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?
A. Immediately send the current weekly status report
B. Add email to the distribution list for the weekly status report
C. Remove email from the distribution list for the monthly status report
D. Consult the communications plan and act accordingly