CompTIA Project+ PK0-004 – Question436

A project manager is assigned to a project with an unfamiliar domain area. The project manager is compiling a list of stakeholders and their roles in a chart. The project manager lists SMEs in the project domain to be:

A.
delegated
B. instructed
C. consulted
D. employed

Correct Answer: C