CompTIA Project+ PK0-004 – Question444

Many questions have arisen regarding a newly identified project. Project team members are anxious to know who will be part of the team and what the project will deliver. Which of the following would be the BEST way to provide this information?

A.
Kickoff meeting
B. Status report
C. Company-wide email
D. CCB meeting

Correct Answer: A