CompTIA Project+ PK0-004 – Question450

Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?

A.
Resources
B. Requirements
C. Scope
D. Funding

Correct Answer: D