CompTIA Project+ PK0-004 – Question461

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?

A.
Submit a change request to the CCB.
B. Implement the change to the project.
C. Determine the impact of the requested change.
D. Update the schedule to accommodate the change.

Correct Answer: C