CompTIA Project+ PK0-004 – Question482

A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?

A.
Provide the next task to the newly freed resource.
B. Communicate the success to the team.
C. Notify the project sponsor of the new completion date.
D. Update the schedule and add lag to the next task.

Correct Answer: B