A project sponsor promises the Chief Executive Officer (CEO) that a project will be completed before the next quarterly meeting. The project manager needs to take the following elements into account:
– Delivery
– Vacation
– Cost of overtime
– Work effort
Which of the following documents should the project manager use to guarantee the project's success?
A. RACI
B. Schedule
C. Project charter
D. SWOT
E. Burn chart
– Delivery
– Vacation
– Cost of overtime
– Work effort
Which of the following documents should the project manager use to guarantee the project's success?
A. RACI
B. Schedule
C. Project charter
D. SWOT
E. Burn chart