A concrete pad needs to be laid for a new house and requires three days to cure. The project manager notes that rain may be in the immediate forecast.
Which of the following would BEST avoid the risk of rain damage?

A.
Place a tarp over the fresh concrete to protect it.
B. Refinish the concrete if it rains during that time.
C. Pour the concrete as quickly as possible to allow the most drying time.
D. Wait to pour the concrete until rain is not in the forecast.

Correct Answer: C