CompTIA Project+ PK0-004 – Question046

A project manager is working on the project charter.
Which of the following phases does this describe?

A.
Initiation
B. Planning
C. Execution
D. Closing

Correct Answer: A

Explanation:

Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107