CompTIA Project+ PK0-004 – Question539

Which of the following metrics are used to determine a project's EAC?

A.
Baseline costs plus actual costs
B. Forecasted costs plus actual costs
C. Planned costs minus actual costs
D. Forecasted costs minus actual costs