CompTIA Project+ PK0-004 – Question541

A project manager has received documented approval from management to begin a project and the authority to start assigning resources to the project.
The project manager has received the:

A.
project charter.
B. statement of work.
C. project plan.
D. project request.

Correct Answer: A

Explanation: