CompTIA Project+ PK0-004 – Question554

Because of space limitations, there has been a long history of contention among the team.
Which of the following actions can the project manager take that would MOST contribute to a successful project?

A.
Ignore the issue.
B. Require staff to focus on deliverables.
C. Replace team members.
D. Hold an open dialogue to build consensus.

Correct Answer: D