CompTIA Project+ PK0-004 – Question568

A project manager recently joined a projectized organization and is having many issues on five different projects. Which of the following risk activities should be performed FIRST? (Choose two.)

A.
Identify
B. Coordinate
C. Qualify
D. Brainstorm
E. Mitigate
F. Assign

Correct Answer: AB