CompTIA Project+ PK0-004 – Question571

A project manager receives an initial project assignment.
Which of the following documents is MOST likely to indicate the organizational structure for the project?

A.
Communication management plan
B. Baseline
C. Business case
D. Organizational breakdown structure

Correct Answer: C