CompTIA Project+ PK0-004 – Question577

A vendor developed a new payroll system for a local transit authority. Due to the system's complexity, the vendor will need to work with the transit authority for three months after system implementation.
This will be documented in the:

A.
warranty.
B. training plan.
C. WBS.
D. SLA.

Correct Answer: D