CompTIA Project+ PK0-004 – Question589 Which of the following normally would be completed prior to a vendor responding to an RFP?A. POB. ContractC. SLAD. NDA Show Answer Hide Answer Correct Answer: D Post navigation CompTIA Project+ PK0-004 – Question588CompTIA Project+ PK0-004 – Question590