CompTIA Project+ PK0-004 – Question590

A project team is brainstorming and documenting what might go wrong in a project, the possible impact, and potential actions should certain situations arise.
Which of the following contains actions the team is MOST likely to consider?

A.
Identify, collaborate, quantify
B. Accept, mitigate, transfer
C. Stop, review, plan
D. Prioritize, qualify, engage

Correct Answer: A

Explanation: