CompTIA Project+ PK0-004 – Question621

During a routine risk review, the project champion analyzes the status of multiple projects. A potential risk is discovered that will delay project A due to the interdependencies with project B. The project champion schedules a meeting with the project managers. Which of the following risk activities is MOST likely happening?

A.
Identification
B. Registration
C. Quantification
D. Qualification

Correct Answer: A

Explanation:

Explanation:
All projects have risks. Risk identification is the process of determining and documenting the potential risks that could occur on your project.