A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables.
Which of the following steps should the project manager take to BEST resolve the issue?
A. Ask the project sponsor for shared resources for the key stakeholder's project.
B. Ask the project sponsor for benched resources for the time-sensitive project.
C. Ask the key stakeholder for low-quality resources for the time-sensitive project.
D. Ask the project sponsor for dedicated resources for the time-sensitive project.