CompTIA Project+ PK0-004 – Question635

A project manager is planning a wedding that will take place during the rainy season. The possibility of rain is very high, so the project manager proposes alternatives to having an outdoor wedding.
This is an example of:

A.
mitigation.
B. acceptance.
C. exploitation.
D. transference.

Correct Answer: A

Explanation:

Explanation:
Mitigation is to reduce the probability or impact of a risk.