CompTIA Project+ PK0-004 – Question637

A finance company hired a software consulting company to develop a new system. During the testing phase, the finance company's testing team found a major defect. The software consulting company states the software was constructed per the approved design.
Which of the following documents should be used to clarify the situation?

A.
Letter of intent
B. Requirements document
C. Statement of work
D. Service-level agreement

Correct Answer: D