During a project status meeting, the project manager states the project is running ahead of schedule. However, the executive committee, which is unfamiliar with the project manager's work, does not think it will finish on time.
Which of the following is the MOST likely cause?
A. personal preferences
B. Interorganizational differences
C. Relationship building
D. Specific communication
Which of the following is the MOST likely cause?
A. personal preferences
B. Interorganizational differences
C. Relationship building
D. Specific communication