A project team is currently three weeks behind in a project with six more weeks to go. Although the project manager believes the project can be fast tracked to save a week, this is not the case.
Which of the following represents the slack along the critical path?
A. -3 weeks
B. -2 weeks
C. 0 weeks
D. 2 weeks
E. 3 weeks